Laying Guidelines for English Timbers Solid Floors
Index
The following is a general indication of how to lay particular types
of hardwood flooring.
Ultimately it is up to the floor layer to check
site conditions, decide on the basis of experience and the site conditions
which methods to apply, whether to acclimatise the floor and if so
for how long and the amount of expansion allowance etc.
Fitting instructions
are supplied to all new customers and packed with the delivered flooring.
For more information please refer to the section on "Site
Conditions" and also to the section on "Site
Survey & Predicting the performance of Wood Floors."
Acclimatisation
The acclimatisation of a new wood floor
prior to laying has been accepted practice for many years. Some
recent experiences have lead us to doubt some of the accepted wisdom
and initial research has indicated that acclimatisation can, in some
circumstances, lead to problems. This is the subject of ongoing research
by ourselves, but the fitter should consider the following:-
The site conditions at the time of laying the floor should always
be the same as those expected in service. The building fabric must
be thoroughly dried out and the ambient temperature and relative humidity
be as specified in the "Site Conditions"
section.
If the site conditions differ significantly from those specified
then the equilibrium moisture content will be different from the actual
average moisture content of the new flooring and considerable movement
may take place. A competent site survey will determine the actual
site conditions.
New timber flooring should only be delivered to site when the site
conditions are correct. If not, it is likely that some of the
flooring will absorb moisture from the surrounding air or structure
of the building and expand and distort.
If the contractor chooses to acclimatise
the flooring, the process may take significantly longer than the accepted
7 to 14 days. It must be stacked in the room where it is to be laid
so that each separate piece of flooring is exposed to circulating air
on all four sides and the air circulation improved using a fan for the
best results. It is not acceptable to simply leave the bundles, unopened
in the room where it is to be laid. Only the outer boards of each bundle
will acclimatise and only on the outer face.
The acclimatisation period required to significantly change the
moisture content may be much longer than 14 days and in some tests
the period was as much as 10 weeks to change the moisture content
by about 1.5%. The delay and inconvenience caused by this would
obviously would be unacceptable to the client.
Where the site conditions are significantly different from those specified,
the acclimatisation process may cause the flooring to expand
or contract unevenly and the dimensions to go out of tolerance.
This may result in unsightly gaps between adjacent boards when
the floor is laid and make for a difficult installation.
In situations where the flooring is likely to expand a small, acceptable
amount and, provided that the site conditions are more or less acceptable,
it may be better to allow the flooring to acclimatise after
laying. This means that some estimate of the amount of expansion must
be made and this can be done by comparing the estimated equilibrium
moisture content at the ambient site conditions with the actual moisture
content of the new flooring.
If the floor is likely to expand, leave an adequate
gap around the perimeter and fix the floor using a recommended
pneumatic nailer. This will fix the floor more loosely than a
Powernailer and although there may be a few gaps here and there,
they will close up as the floor adjusts.
This method is suitable only if the site conditions are reasonably
close to those specified. It cannot be used where site conditions
are significantly different because the movement may be too great.
Correct site conditions must be achieved.
This method may offer the optimum solution because the floor dimensions
and machining tolerance are correct at the time of laying and this
makes for an easy installation. Any differences in the expansion rates
of different boards are taken up and equalised within the floor and
boards which could expand more than others are restrained by the adjacent
boards.
The timber should not be taken to site or unwrapped until
the site conditions are correct and this method provides the fitter
with more control over the whole process. For this method to work
effectively it is important to fit the floor with some slack.
If the flooring is acclimatised at incorrect conditions for
a long enough period of time - say for example during or just after
building work when the relative humidity is high - the moisture content
will adjust to these conditions. Once the floor is laid and exposed
to heated conditions, the floor will then shrink and could distort.
If new hardwood flooring is to be fitted over underfloor
heating, the flooring may be acclimatised before laying while the
heating is on and some adjustment may occur. However, it is essential
that sufficient allowance is made for expansion during summer when
the heating is turned off. The previous comments about changes in
dimension still apply and our certificate of moisture content will
help in deciding whether to acclimatise or not. Also see the Underfloor
Heating section in Site Conditions and Expansion
below
Fitting the Floors
English
Timbers floors are tongued, grooved and ends matched and usually 128mm
wide.
The boards are dimensionally stable provided that the site conditions
are correct and stable.
If this is the case they only require fixing by secret nailing at 45 degrees through
the base of the tongue using a 50mm long, serrated T nail.
If conditions
are likely to vary a little, then the 100mm wide is recommended as a maximum for secret
nailing. The wider boards may be used, but facing fixing may also be required.
If this is not carried out, the wider strips may bow slightly across
the face as conditions vary from summer to winter.
Face fixings may be nails
driven vertically through the face and any holes filled or screws and
cross grained wood pellets.
Boards are nailed at about 200mm to 300mm intervals or less
depending on the length of the board and the nature of the sub floor.
The floor must be nailed
frequently to provide sufficient fixings to hold the floor in place
and prevent unnecessary movement.
Nailing at more than 300mm centres
may not provide enough fixings.
Within reason, the more nails used, the better the floor. The best subfloor
is an existing boarded floor or a new ply floorwhich allows the floor to be nailed at any point.
1. Floors fixed to existing boarded floors
Lay new flooring at 45 or 90 degrees to
the direction of the existing boards and nail at intervals of 300mm or less.
The existing sub floor should be in sound
structural condition and level. It is usual to punch in any nails and
check for high points with a straight edge before levelling the existing
floor with a floor sander.
Where the hardwood floor is required to
run in the same direction as the existing boards, it should preferably
be overlaid with dry, exterior grade 9mm plywood (minimum thickness
6mm) which is securely fixed to the original floor. The new floor is fixed through the ply into the existing
floor.
If the floor is a ground floor over a cavity or unheated
room, a vapour barrier, such as Sisalkraft 420 or Novia A1F, should
be placed between the new hardwood floor and the old to prevent
an increase in moisture content of the new. The joints should have an overlap of at least 100mm and may be taped for extra security. Polythene sheet is not recommended in this case because it may sweat. It is advisable, but not essential, to insulate under the
existing floor.
Useful, but not essential advice, is to use a damp proof membrane under all new
floors and not just ground floors. This has the advantage of isolating
the new floor from the sub floor and this prevents any migration of
moisture from the underside during the summer months when the humidity
is high.
2. Floors fixed to existing chipboard or plywood floors
The principle is the same as in 1. with the following exceptions:-
- Flooring should be laid at 45 or
90 degrees to the joists and nailed at 300mm centres or less.
In reality it is normal to nail at about 50mm in from each end
and every 200mm to 300mm centres. A few extra nails costs little
and improves the rigidity and stability of the floor.
- The
chipboard or plywood must be securely fixed to the joists.
Make sure you use a building paper on ground floors. Plywood
is a better subfloor than chipboard because it holds nails
better and there is less chance of the nail breaking out the
underside of the floor especially with face nailing.
Under normal circumstances, our hardwood
floors should not be fixed to a floating chipboard floor because it
is not sufficiently rigid. Any excessive seasonal movement may cause
the floor to expand and perhaps lift the floor. Contraction is not a
problem with a floating floor.
In thoroughly dry, modern buildings with a high level of insulation, the seasonal
variations in floor moisture content are small. A solid
floor could be fixed to a floating floor in these conditions provided
that the chipboard or ply is sufficiently thick, very dry and adequately bonded together. The floor slab must be dry and overlaid with visqueen and a building paper laid over the chipboard. Site conditions must be correct and stable.
3. Floors fixed directly to timber joists
This is only acceptable if the joist centres are less than 300mm and should only be considered
if the space below the floor is fully heated. In any event, it is good
practice to first fix 18mm T & G plywood or chipboard for the reasons
listed below.
Hardwood flooring should
not be fixed directly to ground floor joists over a ventilated cavity.
The timber will absorb moisture from the air in the cavity and expand.
It is recommended that an exterior grade plywood or flooring grade
T & G chipboard at least 18mm thick is first fixed to the joists
followed by a vapour barrier such as Novia A1F. Hardwood
flooring is then fixed as in Section 2.
Fixing Chipboard or plywood offers other advantages:-
-
The plywood or chipboard provides a
useful platform for all the second fixings, plaster work etc. and
living, bearing in mind that the hardwood floor can only be fitted
when the house is fully dried out.
-
It makes for easier, safer and faster floor laying.
-
Floor joists are normally set at 400 to 500mm centres and the 18mm thick
board should be used so that the flooring can be nailed at the correct
spacing ie:- 300mm or less.
4. Hardwood floors fixed to softwood battens on concrete
Flooring may be laid over concrete floors by fixing
dry, pre-treated softwood battens to the concrete at the correct centres
(see B. below) and nailing the board at every intersection to a batten
taking note of the following:-
-
The battens may be fixed by gluing with a recommended adhesive or
by screwing and plugging. All fixings should be sunk below the
surface of the batten.
-
The distance between the centres of battens should be less than or
equal to the shortest length of the flooring but no greater than
300mm & preferably less.
-
The minimum thickness for a batten is 25mm (20mm if the nail
is driven at 30º) and the normal width is 44mm. If insulation
is to be laid between the battens, they may need to be 50mm deep
or to suit the depth of insulation. Battens should be laid
in short lengths (1.8 to 2.1 metres) with a 200\250mm overlap (side
to side).
-
The concrete should be level and very dry. As it is difficult
to fully dry out a concrete slab to the necessary relative humidity,
it is necessary to lay an additional vapour barrier above
the concrete.
This may be a non breathable building paper, an applied epoxy
resin membrane or a polythene membrane provided that it
is laid in such a way to prevent condensation.
The type of vapour barrier is really dependant on the humidity of the slab. As a guide line:-
If the RH is dry, say under 60% Novia A1F building paper with taped joints can be used.
If 60% to 75% use a heavy gauge polythene with taped joints.
If over 75% use 2 coats of Sika epoxy DPM. Bond battens to epoxy with Sika T52 or T54. Discuss details with the manufacturers.
-
If no DPM is to be used over slab and under the floor, the concrete slab must be fully dried
out with a maximum relative humidity of 40%. This equates to a moisture content of 2%.
See
Sub-Floors
on the page Site Conditions & Other Factors. The concrete
slab must contain an effective integral damp proof membrane.
In reality it
is difficult to achieve 40% RH in the slab and a DPM must therefore be used
over the slab.
-
Any under floor pipe work should be fully pressure tested prior to
laying the floor. All pipes should be effectively insulated to
prevent hot spots under the floor. If not, this may cause localised
shrinkage.
NB. When nailing hardwood flooring to an existing timber floor,
care should be taken to avoid any under floor services - pipes,
wires etc.
Use of Adhesives Directly to Concrete
During recent years, new adhesives have been developed
along with compatible epoxy DPMs, self levelling compounds etc. Several
contractors are now successfully gluing our floors to concrete sub floors
with these compounds.
Because of the accuracy of our machining
the floors push together to give a reasonably tight fit.
Although we cannot recommend the
methods used, they seem to be reasonably successful to date.
Below is a summary of the methods which have been used, some of the
adhesives used and general comments by the contractors. In our opinion
it is too early to assess the long term success of the methods, but they
are worth considering.
Adhesives successfully used were
-
SikaBond T2 - A gun grade polyurethane
and SikaBond T52 and T54, similar trowel applied equivalents. These would be
the better option in our opinion.
These are flexible adhesives and allow for some movement in the floor.
-
Lecol 5500 - Solvent based floor adhesive.
Non flexible.
-
Rinaldi S1
- Non flexible
The Sika bond T2 was either applied to the back of the flooring as
a bead of glue running across the board every 300mm or less or to
the floor. The boards were pushed into place and held down by weighting with blocks. They were fixed down to the
concrete by screwing and pelleting every 500 or 600mm in a grid layout.
The SikaBond T52 is a similar adhesive which is applied over the
whole area with knotched trowel and, we feel, is more likely to provide
a better fixing. These adhesives will bond directly to the epoxy DPM. Some adhesives do not.
The Lecol and Rinaldi were normally
applied to the sub floor with a knotched trowel or applied thickly to
the back of each piece of flooring before pushing into place. Again
the flooring was fixed down at 500 or 600mm centres by screwing and
pelleting.
The method has the advantage of sticking
directly to concrete and reducing the height of the floor.
The disadvantage is that it has not been proven over a long period of time in the UK, but it has been used in Europe for many years.
For this to be even considered, the concrete
slab must be very dry and have an epoxy mortar surface DPM and the adhesive
must be compatible with the epoxy. The property must have dry stable
conditions.
Please remember that this is an account of
what has been done and we cannot recommend it as a foolproof or proven
method.
Expansion Allowance and Setting Out
English
Timbers floors are machined to very accurate tolerances and the timber
is generally dried to ensure stability in modern heated buildings. In
order to prevent excessive expansion it is essential to make allowances.
Always leave an expansion gap:-
-
Around the perimeter of the room, 10mm to 12mm for a small room and
15mm to 20mm for a larger room.
- As a series of intermediate
expansion gaps across the width of the floor if the
flooring is to be fitted with a powernailer. If not fit with a pneumatic nailer and do not include intermediate expansion allowance. This may be necessary when the floor is
likely to expand after laying and especially with a large floor
where the peripheral allowance may be too little. Flooring laid
during winter with full central heating will mostly expand in summer.
Flooring laid in summer will tend to expand immediately after fitting
and may take several months to reach equilibrium.
Floor laying may be started adjacent to the longest wall, in which
case the first 2 or 3 rows are set to a line & fixed through the
face with the tongues pointing away from the wall.
If the shape is
complicated or includes several rooms, laying may be started part
way across the room.
A line running through the rooms is set out and
adjusted so that the flooring is either parallel to one or more walls
or, if the walls are out of parallel, the best line is followed.
For
this method, two lines of boards are placed groove sides together,
with a loose tongue of plywood inserted into the grooves. Each piece
is face nailed or screwed (and pelleted) to the sub-floor.
Ensure
that these rows are laid in a perfectly straight line with the joint aligned to the string line.
Once the first 2 or 4 rows are face fixed, the rest of the floor is fitted by working outwards
to each side of the centre line leaving expansion gaps where and when
necessary.
With the exception of these first few rows, the boards are fixed using a Powernailer
floor nailer or pneumatic nailer.
Where use is obstructed by
the wall, the boards are either drilled and nailed by hand, face nailed with the appropriate Powernailer face nailer or pneumatic nailer or screwed and pelleted. All flooring is sanded and sealed in situ. Full
fitting instructions are supplied with all strip & plank floors.
For more info on the Powernailers, click here Powernailer
Revised/Checked 19/01/06
Back to the Top